Power plant
| Output | Gen. | Head | Turbines | Year of start-up | Remarks |
MW | GWh/ a | m | Num | Type | Manufact. |
DYCHÓW |
79.5 |
96 |
30 |
2 2 |
K P |
LMZ/V EW/V |
1950
|
Hydropower plant with a pumping unit. Modernization 1997 ÷ 1999. Final modernization (by Energoprojekt 2000 ÷ 2005) - General Contractor.
|
1 2 |
K P |
LMZ/V SFUP/V |
1965
|
CZCHÓW |
8 |
32 |
9 |
2 |
K |
V+Ch |
1954 |
Modernization 2004 ÷ 2005. |
PORĄBKA |
12.5 |
25 |
22 |
2 1 |
K F |
V |
1954 |
Modernization 1995 ÷ 1996 by Energoprojekt - General Contractor. |
PRZEWÓZ |
1.8 |
13 |
4 |
2 |
K |
V |
1956 |
Modernization 1987 ÷ 1988. |
OLSZNA |
1.8 |
4.5 |
6.5 |
2 |
K |
CKD |
1957 |
|
WAŁY ŚLĄSKIE |
9.8 |
45 |
5.5 |
4 |
K |
CKD |
1958 |
Modernization 1994 ÷ 1995.
|
KORONOWO |
26 |
42 |
25 |
2 |
K |
CKD |
1959 |
Hydropower plant with an earth dam. |
TRYSZCZYN |
3.3 |
8 |
4 |
2 |
K |
G-M |
1960 |
|
MYCZKOWCE |
8.4 |
30 |
22.8 |
2 |
K |
G-M/V |
1961 |
Hydropower plant with an earth dam. Modernization 1998 ÷ 2000 by Energoprojekt - General Contractor. |
DĄBIE |
2.94 |
13 |
3.7 |
2 |
K |
G-M |
1962 |
|
SOLINA |
136 200.2 |
112 200 |
60 |
2 2 |
F PT-F |
CKD/V CKD/S |
1968 |
Hydropower plant with a pumping unit and concrete dam. Modernization 2000 ÷ 2003 (capacity increased up to 200.2 MW). |
WŁOCŁAWEK |
160 |
640 |
10 |
6 |
K |
ChGZ |
1970 |
Modernization. |
ŻYDOWO |
150 |
193 |
81 |
2 1 |
PT-F F |
CKD |
1970 |
Pumped-storage hydropower plant. Modernization 2000 ÷ 2012 by Energoprojekt - General Contractor. |
GUBIN |
1.16 |
5.3 |
4.2 |
2 |
K |
SMW |
1973 |
Modernization of two hydro turbine sets.
|
PORĄBKA-ŻAR |
500 |
640 |
439 |
4 |
PT-F |
B+CDK |
1979 |
Pumped-storage hydropower plant. Reconstruction of the upper reservoir in 1995 by Energoprojekt - General Contractor. |
2014 |
Concept of modernization (planned in 2015÷2021). |
ŻARNOWIEC |
680 |
1165 |
119.3 |
4 |
PT-F |
CKD |
1982 |
Pumped-storage hydropower plant. Reconstruction of the upper reservoir in 2006. Modernization of 4 hydro turbine sets by Energoprojekt (2007÷2011) - General Contractor. |
MŁOTY |
750 |
1200 |
271.6 |
3 |
PT-F |
(CKD) |
design |
Pumped-storage hydropower plant. |
CZORSZTYN - NIEDZICA |
93 |
128 |
46.1 |
2 |
PT-DR |
CKD |
1997 |
Hydropower plant with a pumping unit. |
SROMOWCE WYŻNE |
2.08 |
7.5 |
9.5 |
4 |
FL |
FL |
1994 |
Design and development by Energoprojekt - General Contractor. |
JEZIORSKO |
4.9 |
21 |
6.5 |
2 |
K |
ZRE |
1994 |
|
SOBOLICE |
0.66 |
3.9 |
3.2 |
2 |
K |
D |
1993 |
Modernization. |
KLICZKÓW |
0.64 |
2.65 |
5.9 |
2 |
FL |
FL |
1994 |
|
DOBCZYCE |
2.24 |
6.8 |
28.6 |
2 |
K |
CKD |
1993 |
|
KLIMKÓWKA |
13 |
5.4 |
30.5 |
1 |
K |
CKD |
1994 |
|
MAŁOMICE |
0.80 |
3.1 |
2.7 |
2 |
K |
D |
1992 |
Modernization. |
MAZIARNIA |
0,05 |
0.3 |
6.9 |
1 |
B-M |
ZRE |
1985 |
|
BUKÓWKA |
0.84 |
5.4 |
5.6 |
2 |
FL |
FL |
1992 |
|
ŚWINNA PORĘBA |
4.0 0.1 |
18 |
37.6 |
2 1 |
K RK |
ZRE ZRE |
2017 |
Hydropower plant and a water reservoir. |
NYSA |
0.27 |
1.8 |
3.5 |
1 |
FL |
FL |
1993 |
Replacement of 1 hydro turbine-generator set by Energoprojekt - General Contractor. |
TOPOLA |
1.56 |
6.85 |
6.5 |
3 |
FL |
FL |
2002 |
Energoprojekt - General Contractor. |
ZASIEKI |
0.82 |
5 |
3.7 |
2 |
K |
D |
1996 |
Modernization of hydropower plant and weir in 2004. |
SIEMIANÓWKA |
0.16 |
1.1 |
7 |
2 |
FL |
FL |
1996 |
Design, site supervision and start-up. |
GORZUPIA |
1.68 |
10.1 |
4.6 |
4 |
FL |
FL |
1998 |
|
ŻAGAŃ I |
0.9 |
4.8 |
2.8 |
3 |
RK |
M |
1998 |
Modernization. |
KĘPKA |
0.52 |
2.3 |
4.4 |
2 |
K |
ZRE |
1998 |
Reconstruction. |
SZPROTAWA |
0.63 |
3.7 |
2.9 |
2 |
RK |
M |
1998 |
|
MALCZYCE |
9.0 |
45.7 |
5.8 |
3 |
RKG |
- |
under construction |
Construction Permit Design - 2006. Detailed design - 2007 (upgrade in 2015). Under construction (2005 ÷2019) by Energoprojekt - General Contractor. |
ROŻNÓW |
50 |
102 |
29.7 |
4 |
K |
EW |
2000
|
Modernization of 4 hydro turbine sets by Energoprojekt (1996÷2000) - General Contractor. |
PRZYSIEKA |
1.3 |
6.57 |
5.4 |
2 |
RK |
S |
2001 |
|
RAKOWICE |
1.8 |
9.1 |
8.6 |
2 |
RK |
M |
2005 |
|
TRZEBIATÓW |
0.25 |
1.9 |
2.6 |
1 |
RK |
M |
2001 |
|
JANUSZKOWICE |
1.4 |
7.1 |
2.6 |
2 |
RK |
VA - TECH |
2003 |
|
KRĘPNA |
1.26 |
7.0 |
2.5 |
2 |
RK |
M |
2004 |
|
KRAPKOWICE |
1.26 |
7.28 |
2.6 |
2 |
RK |
M |
2006 |
|
ZIELISKO |
1.36 |
5.8 |
3.6 |
3 |
RK |
M |
2002 |
Replacement of 2 hydro turbine-generator sets and modernization of the third one.
|
WIELOWIEŚ KLASZTORNA |
0.7 |
3.2 |
10.5 |
2 |
- |
- |
design |
Hydropower plant with a lifting weir. |
SMOLICE |
1.3 |
6.9 |
3.6 |
2 |
RK |
M |
2006 |
|
BOBROWICE III |
1.1 |
5.6 |
9.6 |
2 |
- |
- |
design |
Concept development. |
DOBRZEŃ |
1.6 |
10.0 |
2.1 |
2 |
RK |
M |
2008 |
Comprehensive design - construction of a hydropower plant at the existing barrage. |
CZANIEC |
0,4 |
1,3 |
9,3 |
1 |
RK |
- |
design |
|
JANOWICE |
1.52 |
10.65 |
3.7 |
4 |
RK |
GEG |
2011 |
Modernization. Replacement of 4 hydro turbine-generator sets. |
BRZEG |
0.4 |
2.0 |
2.5 |
1 |
K |
GEG |
2012 |
Modernization. Replacement of 1 hydro turbine-generator set and process equipment. |
BYSTRZYCA KŁODZKA |
0.4 |
1.3 |
6.5 |
2 |
- |
- |
design |
Modernization. |
RZESZÓW |
0.66 |
3.0 |
6.0 |
1 |
K |
M |
2012 |
Hydropower plant with a fish pass by the existing stage. |
POŁOCKA (Białoruś) |
20.0 |
90.0 |
7.7 |
5 |
RKG |
- |
design |
Construction Permit Design. |
RADUSZEC STARY |
3.0 |
15.0 |
4.8 |
2 |
K |
V |
design |
Modernization. |
CHAŃCZA |
0.16 |
1.1 |
12.0 |
1 |
RK |
- |
2013 |
Installation of a small hydro turbine-generator set. |
PILCHOWICE I |
(7.58) 11.8 |
|
35.0 |
4 2 |
|
ZRE V |
2015 |
Modernization. Increase of installed capacity. Replacement of four hydro turbine-generator sets. Refit of two hydro turbine-generator sets. |
BOBROWICE I |
(2.42) 3.5 |
|
14.0 |
2 1 |
K F |
GEG V |
2016 |
Modernization. Increase of installed capacity. Replacement of two hydro turbine-generator sets (1 x 1.52 MW). Refit of third one. |
OTMUCHÓW |
(4.8) 6.0 |
|
18.0 |
2 |
K |
CKD |
2014 |
Modernization. Replacement of 2 hydro turbine-generator sets. Increase of installed capacity. |
BRANIEWO |
0.6 |
1.9 |
2.5 |
2 |
K
|
- |
design |
Concept of modernization. |
OŁAWA |
|
|
|
|
|
M |
2013 |
Construction Permit Design. Technical Adviser services. |
DĘBE |
20.0 |
91.0 |
5.7 |
4 |
K |
G-M |
design |
Modernization of electrical devices. |
SZKLARSKA PORĘBA I |
0.74 |
3.0 |
45.5 |
2 |
F |
ZRE |
design |
Modernization of hydropower plant. |
GŁĘBINÓW |
3.04 |
|
9.5 |
2 |
RK |
G-M |
2016 |
Modernization of hydropower plant. |
MARSZOWICE |
0.38 |
1.12 |
3.75 |
2 |
F |
V |
design |
Multi-variant concept - modernization or replacement of devices. |
NIEDZICZANKA |
0.17 |
0.3 |
1÷5.7 |
1 |
RK |
- |
design |
Sromowce Wyżne water reservoir - "low water" |
ZWANOWICE |
1.8 |
8.5 |
3.5 |
2 |
K |
- |
design |
Construction Permit Design of a new hydropower plant at the existing barrage. |
KĄTY OPOLSKIE |
1.5 |
7.3 |
2.15 |
2 |
RK |
- |
design |
Construction Permit Design of a new hydropower plant at the existing barrage.
|
WRÓBLIN |
1.7 |
8.5 |
2.5 |
2 |
RK |
- |
design |
Construction Permit Design of a new hydropower plant at the existing barrage.
|
LIPKI |
2.1 |
11.0 |
2.2 |
3 |
RK |
M |
2017 |
Detailed design of a new hydropower plant at the existing barrage (electrical and mechanical parts).
|