Power plant, type, capacity | Completion time | Scope of services |
| Start | End | |
PORĄBKA-ŻAR / 500 MW pumped – storage hydro power plant |
2017 |
2019 |
Comprehensive replacement of 2 ball valves (Dn 1650, Pn 6.6 MPa) for hydro turbine sets TZ3 & TZ4 - technical documentation, supply, assembly and start-up. |
2014 |
2016 |
Comprehensive replacement of 2 ball valves (Dn 1650, Pn 6.6 MPa) for hydro turbine sets TZ1 & TZ2 - technical documentation, supply, assembly and start-up. |
TUPOŁANG / 180 MW hydro power plant (Republic of Uzbekistan) |
2015 |
2020 |
GENERAL DESIGNER - extension and replacement of the electrical and mechanical equipment. A capacity increase of the small hydro sets (from 2 x 7.5 MW to 2 x 15 MW). Mounting of the new hydro sets (2 x 75 MW). |
GŁĘBINÓW / 3040 kW hydro power plant |
2013 |
2016 |
Comprehensive modernization of a power plant including a replacement of 2 hydro turbine sets and a construction of new substation. |
OTMUCHÓW / 7500 kW hydro power plant |
2012 |
2014 |
Comprehensive modernization of a power plant including a replacement of 3 hydro turbine sets. |
ŻYDOWO / 150 MW pumped – storage hydro power plant |
2008 |
2013 |
Comprehensive modernization of a power plant and a head canal. Investor Representation. |
MALCZYCE / 9000 kW hydro power plant |
2005 |
2020 |
Delivery and assembly of a technological equipment. |
ŻARNOWIEC / 680 MW pumped – storage hydro power plant |
2010 |
2011 |
Comprehensive modernization of HZ-2 hydro turbine set. |
2009 |
2010 |
Comprehensive modernization of HZ-1 hydro turbine set. |
2008
|
2009
|
Comprehensive modernization of HZ-3 hydro turbine set.
|
2007 |
2008 |
Comprehensive modernization of HZ-4 hydro turbine set. |
ŻARNOWIEC / 680 MW pumped – storage hydro power plant |
2016 |
2016 |
Reconstruction of mastic seal of the upper reservoir (area of around 70 000 m2).
|
2006 |
2006 |
Reconstruction of asphaltic concrete lining of the upper reservoir (area of around 240 000 m2).
|
DYCHÓW / 90 MW storage hydro power plant
|
2003 |
2005 |
Comprehensive modernization of a power plant. |
CZCHÓW / 8 MW hydro power plant
|
2004 |
2005 |
Delivery, assembly and start-up of a turbine controller set. |
SOLINA / 200 MW storage hydro power plant
|
2001 |
2003 |
Investor Representation and General Supplier. Comprehensive modernization and expansion of a 110 kV substation. |
PORĄBKA-ŻAR / 500 MW pumped – storage hydro power plant
|
2001 |
2002 |
Modernization of a settlement system and a 220 kV substation. |
TOPOLA / 1560 kW hydro power plant
|
1994 |
2002 |
Construction of a plant`s technological equipment excluding a civil part. |
SOLINA / 200 MW pumped – storage hydro power plant
|
2000 |
2002 |
Comprehensive modernization and total output increase from 137.6 MW to 200.2 MW. |
ROŻNÓW / 50 MW hydro power plant |
1996 |
2000 |
Comprehensive modernization of a power plant - 4 hydro turbine sets. |
MYCZKOWCE / 8400 kW hydro power plant |
1998 |
2000 |
Comprehensive modernization of a power plant - (2 x 4.2 MW). |
ŁÓDŹ IV / 700 MW combined heat and power plant
|
1996 |
1999 |
Comprehensive modernization of 4 electrostatic precipitators for boilers OP 230 and WP 120. |
GORZUPIA / 4 x 420 kW hydro power plant |
1997 |
1998 |
Project management. |
SIEMIANÓWKA / 160 kW hydro power plant |
1995 |
1996 |
Design, basic deliveries and start-up. |
PORĄBKA / 12,5 MW hydro power plant
|
1994 |
1996 |
Modernization of a power plant (mechanical, electrical and structural part). |
PORĄBKA-ŻAR / 500 MW pumped – storage hydro power plant
|
1995 |
1995 |
Replacement of a sealing in the upper reservoir escarpment. |
SROMOWCE / 2080 kW hydro power plant
|
1993 |
1994 |
Construction of a plant`s technological equipment excluding a civil part. |
NYSA / 270 kW hydro power plant
|
1993 |
1993 |
Comprehensive replacement of a hydro turbine set. |